Project Overview
Stage
Under Construction
Year complete / due
2027
Value
$
4000000
Lot size
2746
sqm
Harnest is delivering seven Class 1a Retirement Living dwellings across two sites in Murray Bridge for RSL Care SA. The staged redevelopment covers demolition, civil works, authority approvals and full construction, all within a live residential environment.
The Outcome
Seven single-storey Class 1a dwellings across two sites: five detached dwellings on Site 1 (Stage 2) and two semi-detached dwellings on Site 2 (Stage 3).
Key features include:
- Staged redevelopment of two separate residential sites, keeping the surrounding community operational throughout
- Class 1a construction in a single-storey detached and semi-detached form
- End-to-end delivery from demolition and civil works through to authority approvals and completion
- Community benefit: new retirement living housing on existing sites, alongside the neighbours who already call the area home.
The Method
Harnest is managing the staged delivery through disciplined program management, early authority engagement and structured communication with neighbouring residents.
- Resolving documentation: Early in construction on Stage 3, we uncovered several inground services that weren't shown in the project documentation. This caused delays and unbudgeted costs. It also meant the footings for Dwelling 2 needed a minor redesign. We worked with the client to get approvals quickly, had the drawings re-engineered and recertified, and brought the footing contractor back to site as soon as possible to limit further lost time.
- Approvals under constraint: The client's concept design had tight site boundaries, so a fire engineering report was needed during building rules consent. We coordinated the report to keep the approval moving. The client had arranged the design and payment of electrical infrastructure upgrades for the site. We took over coordination of these with our engineer and booked the works in line with the construction program.
- Safety on a constrained site: The site is close to existing RSL Care SAresidents, so we fenced it securely to stop anyone walking through and being injured. It also sits on a large parcel of shared land. We put bunting along the access road to keep construction activity off the surrounding land and environment.
- Working beside residents: The site adjoins occupied housing. Our Site Supervisor introduced themselves to residents, shared a two-week look-ahead program, routed construction traffic away from the village, held noisy work until after 8:00 am and used sprinklers to suppress dust.
The Impact
This project demonstrates Harnest's ability to manage a staged, multi-site redevelopment from demolition to completion while neighbouring homes remain occupied.
The project is tracking to the contracted program, with documentation issues resolved and cost-saving options offered.
Murray Bridge forms part of a repeat engagement with RSL Care SA alongside Wallaroo, with governance that meets government funding requirements and a reusable model for future small-scale housing.